1993 Rocky Mountain Arsenal Waste Water Treatment Plant Cost: $850,000 |
Scope: |
Construct a four cell waste water lagoon system and two individual treatment systems, including 100,000 CYS of cut and fill; 600,000 SYS of impervious liner and covering; 14,000 TNS of rip-rap and bedding; 18,000 SYS of filter fabric; 4,000 LF of sanitary sewer with a pump lift station and ultrasonic flow metering flumes. This project, required safety training specific to The Rocky Mountain Arsenal, including specialized Hazcom training and confined space entry training and monitoring. Hudick Excavating, Inc. earned the U. S. Army Corps of Engineers Outstanding Contractor Award for this project. |